I am writing to inform you that we plan to close the A47 so that we can carry out drainage replacement and repair work between the Station Road and Carr Lane overpasses, Wendling. Once complete, the road will be able to better disperse surface water and will be less prone to flooding.
We plan to complete this work over three weeks starting Monday 23 May, between 8pm and 6am, weeknights only. No work will take place over the Jubilee Bank Holiday (Wednesday 1 June and Friday 3 June).
To facilitate this work, temporary traffic signals will be in place on the A47 near the Station Road and Carr Lane overpasses. Whilst we are working, access to all properties and roads in the area will be maintained at all times.
To find out more about road improvements we’re carrying out across the East of England, please visit our website at www.highwaysengland.co.uk/our-work/east/ . If you would like more information, please contact us on 0300 123 5000, or by email at info@highwaysengland.co.uk